Sl.No Item Name Quantity
1 INVERTERS : Supply of solar string inverter-10 kVA rating as per the detailed specifications mentioned in part-A annexure2, sl no 6.2 2Sets
2 COMMISSIONING : Installation, commissioning and Testing of 10 kVA solar inverter with all the installation materials and Civil works etc complete 2Sets
3 INVERTERS : Supply of solar string inverter- 20 kVA rating as per the detailed specifications mentioned in part-A annexure2, sl no 6.2 4Sets
4 COMMISSIONING : Installation, commissioning and Testing of 20 kVA solar inverter with all the installation materials and Civil works etc complete 4Sets
5 CABLE :Supply, laying and interconnecting 4 sqmm 1.1kV grade power cable as per annexure-2 sl no.6.3 for solar power applications 1,500m
6 Solar Panels :Supply and installation of 250Wp, 36 V solar PV module as per the detailed specification in part-A, annexure-2, sl no.6.1 10Nos.
7 Civil services : Supply and providing RCC pedestal as per teh details mentioned in part-A, Annexure-2, sl no.6.6 140Nos.
8 CABLE TRAY : Supply and installation of GI perforated cable tray 15mm width X 50mm height and 2.5 to 3mm thickness as per the detailed specifications in annexure-2 , slno 6.5 350m
9 PIPE : Supply and laying of suitable size CPVC pipe (minimum 20- 25 mm dia) with all the fixing hard wares etc as per detailed specifications mentioned in part-A annexure-2, sl no.6.4 400m
10 AMC for AC installations :AMC for the solar power plant as per detailed specifications mentioned in part-A, Annexure-1 and 2 for first year. 1Yearly
11 AMC for AC installations :AMC for the solar power plant as per detailed specifications mentioned in part-A, Annexure-1 and 2 for second year. 1Yearly
12 AMC for AC installations :AMC for the solar power plant as per detailed specifications mentioned in part-A, Annexure-1 and 2 for third year. 1Yearly
13 AMC for AC installations :AM C for the solar power plant as per detailed specifications mentioned in part-A, Annexure-1 and 2 for fourth year. 1Yearly
14 AMC for AC installations : AMC for the solar power plant as per detailed specifications mentioned in part-A, Annexure-1 and 2 for fifth year. 1Yearly